Define the budget boundary before comparing prices
Record the office area, unit condition, intended headcount and essential operational needs. Identify whether the project starts with a shell, an existing fitted office or a space requiring strip-out. List what will be retained and what must change. These decisions influence both the visible finishes and the technical work supporting them.
Agree what the total project budget is intended to include. Separate contractor works from professional appointments, direct purchases and business relocation costs. RICS describes cost planning as a structured part of construction cost management; for a tenant, the practical lesson is to organise the full project costs consistently rather than compare a detailed proposal with an unexplained total.
Break construction into coordinated work packages
Ask for a breakdown covering the relevant partitions, ceilings, floors, doors, finishes and joinery. Then identify electrical, mechanical, plumbing, lighting, data and other systems within the actual brief. Record the interfaces: for example, whether a meeting-room package includes the room enclosure, power, furniture and technology or only one of those elements.
Show assumptions beside allowances. If a layout, specification or quantity is unresolved, identify what the allowance covers and when it will be replaced with a confirmed amount. A low allowance is not a saving if the intended requirement has simply been omitted. Review alternatives against function and the agreed brief, not price alone.
Add furniture, technology and direct purchases
Create a separate list for desks, seating, storage, meeting-room furniture, equipment and items bought directly by the business. Confirm who provides delivery, assembly, connections and final placement. An item can appear in two quotations or in neither when the contractor and purchasing team each assume the other has included it.
Involve the people responsible for IT and operations early. Establish the requirements for connectivity, access systems and meeting-room equipment, including any supplier appointments or subscriptions the business needs to arrange. Confirm the exact scope and current commercial terms with those suppliers rather than treating technology as a single unexplained furniture allowance.
Record building requirements and project costs
Review the landlord’s fit-out manual and the applicable approval route with the appointed team. Identify submission coordination, specialist appointments, inspections and any building-related deposits or charges that apply to this unit. Keep refundable deposits separate from final expenditure so the cash requirement and expected project cost remain understandable.
Completion requirements also belong in the plan. Dubai Development Authority publishes a fit-out completion service for projects within its jurisdiction; this is not a universal approval route for every Dubai office. Ask the responsible team to confirm the building-specific process and the activities to allow for. Obtain current amounts and conditions directly rather than inserting generic approval fees.
Manage uncertainty and the move-in requirement
List the unresolved risks that may affect cost, such as unknown existing conditions, incomplete design information or an unconfirmed equipment selection. Agree an appropriate contingency with the responsible cost adviser or project team using those actual risks. Keep it separate from known scope and update it as information becomes available.
Track approved changes and committed orders alongside the forecast final cost. A quotation that remains unchanged on paper may no longer represent the project after several client decisions. Include the relevant moving, temporary-operation and final setup costs in the business plan. Review the forecast at decision points so substitutions and scope changes are assessed before commitments are made.
Common questions
Is a cost-per-square-foot rate enough to set an office fit-out budget?
It can be an early comparison reference only when its scope and assumptions are clear. A project-specific budget needs the unit condition, layout, specification, technical requirements and excluded business purchases.
How much contingency should an office fit-out include?
There is no single percentage suitable for every project. Discuss the unresolved risks, available design information and procurement status with the appointed cost adviser or project team.
Are furniture, IT and approvals included in a fit-out quotation?
Only where the written scope includes them. Check each quotation and list the client’s direct purchases, specialist appointments and building-related costs separately.
Further reading
- RICS: New Rules of Measurement and cost planning
- Dubai Development Authority: fit-out completion certificate