Ask IT to issue a project requirements schedule
Request the equipment strategy, connectivity needs, planned cabinet locations and relevant supplier information. Distinguish business requirements from the detailed technical design that the appointed specialists must provide. Record any external connectivity arrangements and the party responsible for them.
Give the fit-out team a clear list of interfaces rather than a general instruction to provide data points. Equipment dimensions, power, access and environmental requirements should come from the responsible suppliers and designers.
Choose the comms-room location with the specialists
Review available space, access, maintenance and routing alongside the office layout. Ask the IT and mechanical specialists to assess the environment needed for the actual equipment. Do not prescribe a universal room size or cooling capacity from a generic office guide.
Show the proposed equipment and access condition on the coordinated plan. Consider who will enter the room, how equipment will be replaced and how other services pass nearby. Resolve those questions before the room becomes a leftover space behind the main layout.
Coordinate cable routes before ceilings close
Agree the routes and containment interfaces with the responsible electrical and IT teams. Identify cabinet entries, floor or ceiling distribution and the locations serving desks and meeting rooms. Keep the documentation consistent as furniture layouts change.
Define inspection and test responsibilities before work is concealed. Ask for labelling and records that the future support team can understand. A visual check of completed outlets does not establish that the network has been tested for its intended use.
Separate building power from technology backup
Ask the appropriate specialists to define normal supply, any backup provision and the limits of each arrangement. Record who supplies, installs, configures and maintains equipment such as UPS units where included. A socket schedule alone does not explain business continuity.
Review landlord restrictions and any requirements for the planned work with the appointed project team. Keep specialist design and approvals responsibilities explicit. Changes to equipment after design approval should trigger a review of the affected interfaces.
Plan a joint handover test
Agree what construction completion, IT readiness and operational acceptance mean. Coordinate testing, connectivity activation, device installation and staff relocation. Allow time for the responsible providers to resolve defects before the office opening.
Send Story and Core the unit plans and IT provider’s requirements at the briefing stage. The proposal can then identify the fit-out interfaces, specialist appointments and handover dependencies that need to be managed together.
Common questions
Is IT always included in a fit-out quotation?
No. Clarify cabling, active equipment, connectivity, configuration and testing separately in the written scope.
Can we decide the server-room requirements after construction?
Late decisions can affect space, power, cooling and routing. Involve the responsible IT and services specialists during design.
Related planning guides
Approval-process reference
Dubai Development Authority: fit-out permit and fit-out completion. These processes concern DDA jurisdiction; confirm the applicable route for the actual property and work.